| Phase | Key milestone | Confirmed / indicative timing | Applicant impact | Expected Start date |
|---|---|---|---|---|
| Application Submission | Application window opens | 30 April 2026 | Applicants can submit their applications in TAMS. | |
| Application Submission | Application window closes | 12 August 2026, 23:59 UTC | No further applications can be submitted. | |
| Fee Payment | Evaluation fee payment deadline | 19 August 2026, or seven days after invoice issuance, whichever is later | Full payment is required for the application to proceed. | |
| Administrative Check | Completeness and administrative review | After application closure | ICANN verifies whether applications meet the administrative requirements. | 21 August 2026 to 6th of October |
| Reveal Day | Applied-for strings and public application data are published | Starting on the 7th of October 2026 | Applicants can identify competing strings and potential contention sets. | 7th of October 2026, 18:00 UTC |
| Communication restriction | Applicant in contention are forbidden to discuss the issue | Until contention stops or one string signs a Registry Agreement. | Applicants cannot discuss to resolve the contention on their own. | |
| Replacement period | Applicants are able to choose their backup string. | 8th of October to 21st of October 2026 | Applicants may switch to the replacement string only during this period, and only if their replacement string is eligible. | 8 October to 21 October 2026 |
| String confirmation day | Icann publishes the final list of strings. | 17th of November 2026 | Icann publishes the final list of strings and contention sets. | 17th of November 2026 |
| Deadline for 65% Refund | This is the last day to get a 65% refund of an application fee | 10 days after String Confirmation Day | Until this day, applicants withdrawing can get a 65% refund on their application fees. | 27th of November 2026 is the limit. |
| Community Input | Application comments and governmental input | Following string confirmation Day | Third parties and governments may raise concerns regarding an application. | Start 18th of November 2026 to 16th of March 2027 |
| Objections | Formal objection filing period | Following string confirmation Day | Applications may face String Confusion, Legal Rights, Community or Limited Public Interest objections. | Start 18th of November 2026 to 16th of March 2027 |
| String Evaluation | Applied-for string reviews | Not before end of November | Strings are reviewed under the applicable technical and policy criteria. | End of November minimum. Expected to last 180 days |
| Deadline for the 35 % Refund | This is the last day to get a 35% refund of an application fee | 11 days after String Confirmation Day until the end of String evaluation period. | Until this day, applicants withdrawing can get a 35% refund on their application fees. | From the 28th of November 2026 |
| Priorization Draw | Establishing an order to process the applications. | Semester 1 2027 | This day, the order for the processing of application is drawn. | First half of 2027, after string evaluation period. |
| Applicant and Application Evaluation | Applicant and application assessments | Schedule to be announced | ICANN-appointed panels assess applications against the Guidebook requirements. | |
| Contention Resolution | Resolution of identical or confusingly similar applications | After the relevant evaluation and objection stages | Applicants may need to resolve contention before proceeding. | |
| Community Priority Evaluation | Priority assessment for eligible community applications | Where applicable; schedule to be announced | A successful community application may prevail within its contention set. | |
| ICANN Auction of Last Resort | Final resolution of unresolved contention sets | Auction calendar not yet published | The remaining eligible applicant wins the right to proceed with the string. Private auctions are prohibited. | |
| Deadline for the 20 % Refund | This is the last day to get a 20% refund of an application fee | Until contracting. | Until contracting with ICANN, applicants withdrawing can get a 20% refund on their application fees. | |
| Contracting | Execution of the Registry Agreement | Following successful completion of applicable processes | Successful applicants enter into a Registry Agreement with ICANN. | |
| Pre-Delegation and Delegation | Technical onboarding and addition to the DNS root | Following contracting and completion of applicable requirements | The new gTLD may be delegated and subsequently launched. | Expected 2028 |
Timeline colour key
Green — Finished step
Yellow — Ongoing step
Grey — Next step to be started
Orange — Objection windows
Blue — Finance-related steps
Stay up to date
News & Insights
Protect your brand today.
Get in touch today to start your BrandShelter account